ACR-News

 

Ensure clarity with a Commissioning Plan

In this article, Tony Anderson of the CSA details a simple tool that provides clarity to all manner of commissioning projects.

In this article, Tony Anderson of the CSA details a simple tool that provides clarity to all manner of commissioning projects.

For those who have never used one, and those who are unfamiliar with a ‘project specific’ commissioning plan, it can be initially difficult to gauge how beneficial having such a plan in place would be to the testing and commissioning of any project. On the other hand, if you have worked on projects that had a detailed commissioning plan in place, you will undoubtedly know and understand their importance.

So what is a Commissioning Plan?

According to BSRIA’s BG8/2009 “Model Commissioning Plan” in its simplest form it should:

•           Provide general information about the project

•           Identify the commissioning team members during each stage of the commissioning process

•           Define the roles and responsibilities for each commissioning team member

•           Create a schedule of commissioning activities for each stage of the commissioning process

•           Establish documentation requirements associated with the commissioning process

•           Establish communication and reporting procedures for the commissioning process

The Benefits of having a project specific Commissioning Plan

Reflecting on projects that I have been involved with across the UK and overseas, the most successful have benefited from having an accurate and updated commissioning plan.

The commissioning phase of any project is normally the most difficult by its very nature. Systems only near completion towards the end of construction phase and the commissioning phase of a project is generally shoe-horned into a few weeks/months preceding project practical completion or handover.

Testing and commissioning at the latter part of a project is a necessity to allow systems to be tested with the building envelope in a final, or at least advanced, state of completion. This is also when construction teams are eager to get everyone out of zones/floors to close out areas and zones and this is when I have found that the commissioning plan can make a massive difference. The installation team managers at this stage know what the main systems are (as opposed to floor area only) and what is required from them to allow completion of each building service.

Construction teams know what commissioning activities are taking place - a small example is they understand why “commissioning tiles” are not installed for duration of commissioning (reminding them of the cost of replacing ceiling tiles or downtime of removing commissioning access tiles usually helps).

The commissioning teams know what systems are to be commissioned, method statements are approved. They know who to report progress to and how to finalize system paperwork to allow systems to be fully witnessed.

Managers are aware of the process of what systems are being commissioned, where commissioning documentation is being kept and when system will be available for witnessing.

Projects without a Commissioning Plan

I found that the common thread on projects that didn’t have a plan in place was that minor building completion issues lead quickly to major delays in completing the commissioning process. Now how much of this was down to not having a Commissioning Plan in place is difficult to assess, however, the outcome was the same on each project that didn’t have one!

Time and time again commissioning activities were overlooked. A common issue which on the face of it could appear trivial is the fitting out of entire floors with floor tiles and suspended ceilings to give the area “the finished look”. Fitting the tiles out may well help make the area “look” finished, but without commissioned MEP services the area in truth is far from complete. On large scale, complex systems, having to re-access hundreds of tiles, sometimes two or three times, caused major disruption to the commissioning and witnessing of systems.

Additionally, construction team members didn’t realise what was expected from them at each stage of the project. The common issue was they had little or no understanding what a commissioning activity involved – both from a system boundary and duration point of view.

Issues also came from the specialist commissioning teams that were not fully aware of the entire reporting process when completing system. An example being, that if a dry riser witness test was not scheduled or not all witnessing parties invited, the entire system had to be retested in front of the full client witnessing team – including the Building Control Officer.

So if a Commissioning Plan is created, will the testing and commissioning run hassle free?

No, and this is a popular misconception. The document itself isn’t a ’one stop shop’ that lists every possible outcome or prevents any issues arising during the T&C of projects. However, it is a platform that allows discussions to be performed at a very early stage and brings together the entire site team from construction to commissioning, through to Integrated Systems Testing. Each person is aware and has a reference point to responsibilities that are clearly set out for construction and commissioning team members at each stage of a project.

Almost all of the major obstacles I have faced from both sides of the fence with regards to commissioning MEP services in any building, all relate back to not having clear, concise communication between all parties on site. It sounds simple and it is; by gathering everyone involved in the commissioning process and continually discussing the process, requirements and responsibilities – clarity can be added to the commissioning stage of the project.

The IOR Annual Conference – a conference on-demand

Delegates to the IOR Annual Conference taking place from 21 to 22 April will get the chance to access the event live and all sessions and recordings for up six months afterwards providing fantastic value and allowing anyone registering for the event ...

  01-Apr-2021
ACR News

A-Gas partners with Solstice Advanced Materials

A-Gas, a global leader in Lifecycle Refrigerant Management and Solstice Advanced Materials, a global leader in high-performance speciality materials, have signed an agreement aimed at accelerating the transition to low global warming potential (GWP) ...

  19-Jun-2026

Summer is coming - checklist for chillers in summer

With the warmer summer months coming, we recommend you give your chiller a good clean and inspection so equipment can operate efficiently and production can run smoothly.
  17-Apr-2026
https://www.acr-news.com/ensure-clarity-with-a-commissioning-plan