CIAT delivers turnkey chiller replacement at Pentland Brands HQ

CIAT UK has completed a full chiller replacement at the headquarters of Pentland Brands, which manages a portfolio of global sports, fashion and outdoor brands. CIAT is part of Carrier, a leading global provider of innovative heating, ventilating and air conditioning (HVAC), refrigeration, fire, security and building automation technologies.

When the original long-serving CIAT chiller on the roof-top of the company’s head office building in Finchley, north London, came to the end of its operational life, CIAT UK was commissioned to come up with a cost-effective, like-for-like solution.

The new system is based on a high-efficiency AQUACIAT Power chiller (LD ST 1250C), with a cooling capacity of 342.5 kW. Based on smooth-running hermetic scroll compressors, the fully packaged air-cooled chiller offers excellent energy efficiency plus low noise operation. Efficiency is enhanced by the use of an all-aluminium micro-channel heat exchange coil, and axial condenser fans with composite blades with an optimised aerodynamic profile.

“We were keen to have a like-for-like replacement as the previous CIAT chiller had proved very reliable over many years of service,” said Natalie Chapman, senior facilities manager at Pentland Brands. “We worked closely with the CIAT UK team throughout the project, and were very pleased with their attention to detail and the quality of the final result.

 “In particular, we appreciated the emphasis on health and safety at every step of the process, which was a vital element in the project as the building remained fully operational throughout the changeover.”

The project included decommissioning and removal of the existing chiller, and installation of the new unit on the roof-top of the five-storey building. Due to space restrictions on site, this required use of a 45-plus-meter-reach crane for removal of the old chiller and positioning the new unit in its place.

The phased plan, managed by CIAT UK, included installation of new pipework, insulation, valve strainers and electrical connections, including trace heating and cabling and connection to the Building Management System (BMS). Finally, the company commissioned the new chiller and carried out balancing of chilled water flow rates across the system.

Comments

Already Registered?
Sign In
Not Yet Registered?
Register

The IOR Annual Conference – a conference on-demand

Delegates to the IOR Annual Conference taking place from 21 to 22 April will get the chance to access the event live and all sessions and recordings for up six months afterwards providing fantastic value and allowing anyone registering for the event ...

  01-Apr-2021

Evaporative cooling leader celebrates 50 years

Seeley International, Australia’s largest air conditioning and heating manufacturer and global leader renowned for over-the-horizon, energy-efficient cooling and heating products, is celebrating its golden jubilee in 2022 – 50 years of world-leading ...

  28-Sep-2022

If you need to open a solenoid valve manually, you need a SVOM!

"THE SMALL TOOL WITH A BIG ATTRACTION" Available from Refrigeration Wholesalers If you would like to become a distributor please contact sales@fridgenius.co.uk
  30-Jun-2022
ACR News is the number one magazine in the air conditioning and refrigeration industry. Don’t miss out, subscribe today!
Subcribe to ACR News

Diary

Chillventa
BESA National Conference