Ciat delivers chiller replacement at hospital on hottest day

Ciat UK completed a major turnkey project for Bouygues Energies & Services to replace chillers at Central Middlesex Hospital in North London, involving a chiller installation on the hottest day ever recorded in the UK.

Central Middlesex Hospital in North London.

The project included the supply of two high performance air-cooled PowerCiat chillers with a combined cooling capacity of over 1.5mW, management of logistics for removal of existing chillers, as well as installation and commissioning of the new units. The units supply critical cooling for the hospital’s operating theatres, wards, public spaces and administration offices.

The project required careful planning to ensure continuity of cooling to the hospital throughout the changeover, allowing for uninterrupted vital services.

Cammy Singh, project manager, Bouygues E&S FM UK, Central Middlesex Hospital, said: “The chillers were replaced in two stages with a four-week proving stage in between; to ensure cooling could be maintained without pause.

“We were fortunate in that one of the existing chillers was no longer operational, and we were able to remove this first and replace it with one of the new PowerCiat units while the other chiller continued to meet cooling demand.”

He added: “Once we were happy the new Ciat unit was performing well we were able to switch off the legacy chiller and lift the second PowerCiat into position. Installation and commissioning of the second chiller coincided with the hottest day ever recorded in the UK – 38.7 degrees celsius in nearby Cambridge.”

This project included fabrication of new pipework to accommodate the different connections required for the new chillers, managing logistics for lift-and-shift of the old units, installation of the new chillers, and pressure testing, refilling and commissioning.

The new chillers are now being connected to the hospital’s Building Management System to optimise energy efficiency and control of conditions across the building.

Mr Sing commented: “We worked closely throughout with Ciat UK’s contract manager Stephen Brown, who managed the whole process from start to finish in a highly professional manner and delivered a first-class result.”

Comments

Already Registered?
Sign In
Not Yet Registered?
Register

The IOR Annual Conference – a conference on-demand

Delegates to the IOR Annual Conference taking place from 21 to 22 April will get the chance to access the event live and all sessions and recordings for up six months afterwards providing fantastic value and allowing anyone registering for the event ...

  01-Apr-2021

Get a grip on food prep with the new Onyx from Williams

Williams has launched the latest versions of its Onyx prep stations, with a sleek new look complementing the innovative features under the hood that deliver energy efficient performance and ensure food safety....

  16-Apr-2024

Extending the application range of the SEC HD - Electric Expansion Valve Controller Heavy Duty Series

The SEC-HD is now compatible with variety of applications using CO2, hydrocarbon, and HFC refrigerants. Users can select from a range of pressure transducers tailored to their specific application and market requirements.
  20-Feb-2024
https://www.acr-news.com/ciat-delivers-chiller-replacement-at-hospital-on-hottest-day